The Contractor shall perform the Work for Harbour House, 214 Harbour Street, as shown in the Contract Documents listed in Article A-3.
The Contract Price is $4,850,000.00, excluding GST.
5.1 The Owner shall make progress payments monthly, within 28 days after the Payment Certifier issues a certificate for payment.
5.2 The Owner shall retain a holdback of 10% of each progress payment. The holdback shall be released 55 days after the certificate of completion is issued, provided no claim of lien has been filed.
No change to the Work shall be made without a Change Order or a Change Directive signed by the Owner.
The Contractor shall reach Substantial Performance of the Work by June 16, 2028, subject to adjustment under the Contract.